Title: PIRELLI SLATINA LOGISTICS CENTER STAGE 1 AND 2: HALL WITH WAREHOUSE FUNCTION. OFFICES, UTILITIES, PLATFORMS, INTERIOR ALLEYS, PARKING, SIDEWALK, GREEN SPACE, AND LAND FENCING
Location: Slatina City, Olt County
Project description :
This project was developed in two stages. The first and second stages, both completed in 2019, saw the construction of an industrial hall (mono-block building in terms of fire safety regulations), with the main function of tire storage. The secondary functions were represented by administrative spaces, technical annexes, fire pumping station with attached tanks, and water household, together with utilities, landscaping, fencing, and site organization, necessary for the proper functioning.

Client

Pirelli Tyres Romania

Location

Olt

Project type

Logistic Center

Completion

2019

Client

Pirelli Tyres Romania

Location

Olt

Client

Pirelli Tyres Romania

Location

Olt

Client

Pirelli Tyres Romania

Location

Olt

Project type

Logistic Center

Completion

2019
The total built-up area in the first phase of development was 30,000 sqm., while the total built-up area in the second stage of development was 33,000 sqm. The hall for tire storage, in-ground floor mode, was divided into three distinct fire compartments. This hall was the object of construction both in phase 1 and in phase 2 of the development of the industrial ensemble. The administrative space, inside fire compartment 1, has a ground floor and a floor-height regime and belongs into the first stage of development. The exterior technical annexes, outside the building, are separate fire compartments (fire compartment 4), in front of the hall, and are also part of the first stage of development.

The design specialties involved: architecture, monolithic reinforced concrete/masonry, and metal resistance.
Year / Duration of the project: Stage 1 and 2: 2018/2019
Scope of works: DTAC / PTH-DE phase design, preparation of documentation for approval-authorization, supervision of works execution